JL混凝土面板堆石坝面板破损机理反演分析研究

    Back analysis on damage mechanism of concrete face slab of JL CFRD

    • 摘要: JL面板堆石坝最大坝高140.3 m,采用花岗岩和石英斑岩填筑,运行初期大坝出现了止水破坏和面板裂缝等问题,从而出现严重渗漏现象,严重影响大坝正常运行。基于大坝沉降观测数据和面板现场检测资料采用三维精细化数值模拟方法反演研究了JL大坝运行初期面板破损机理,再现了堆石坝体变形过程和混凝土面板应力演化性状。研究认为,大坝初次蓄水时发生的水位骤降导致了面板止水破坏,渗水冲蚀垫层区引起面板脱空,造成蓄水后面板在水压力作用下逐步破损和出现贯穿性裂缝。通过降低水位,对水上破损面板采用覆盖修复、水下破损面板采用浇筑环氧混凝土和脱空区灌浆修复等措施,大坝渗漏量得到有效控制。JL大坝面板破损案例给面板堆石坝设计施工以深刻的启示:面板堆石坝设计施工应保证各坝体分区以及面板与垫层之间的变形协调;运行期应避免水位骤降以防止内水外渗导致止水结构破坏和垫层料细颗粒流失;垫层区、过渡区和堆石区之间应严格满足反滤准则,避免面板开裂后垫层料细颗粒流失而导致的面板受力状态恶化。

       

      Abstract: In this study, JL Concrete Faced-Rockfill Dam (CFRD) has a maximum height of 140.3 m and is constructed using granite and quartz porphyry rockfills. During its initial operation, the dam encountered issues such as water-stop damage, slab cracking, and excessive seepage, which affected its normal operation. This study analyzes the damage mechanism of the slab during the early operation based on settlement data and slab inspection records. By using a 3D refined numerical simulation method, the deformation process of the rockfill dam and the stress evolution of the concrete slab are reproduced. Research indicates that the sudden drop of water level that occurred during the initial impoundment led to the damage of the slab water-stops, seepage erosion of the cushion led to gaps between the slab and the rockfill, which further deteriorated the stress of the slab, resulting in progressive damage and cracks. After lowering the water level, the damaged slab is repaired and the gaps are treated with grouting. The leakage of the dam has been controlled. The case of JL CFRD gives a profound enlightenment to the design and construction of CFRDs: The design and construction of a CFRD should ensure that the deformation between the material zones is coordinated so that the slab is in intimate contact with the cushion. During operation period, sudden drop of water level should be avoided as much as possible to prevent waterstops damage and loss of cushion material. The filter criterion of the cushion zone, transition zone, and rockfill zone should be strictly satisfied to avoid the loss of fine particles of cushion material once the slab cracked, which will lead to further damage of the slab.

       

    /

    返回文章
    返回