2400 m埋深地下实验室洞群布置模式优化研究

邱治强, 高明忠, 谢晶, 张朝鹏, 汪文勇

邱治强, 高明忠, 谢晶, 张朝鹏, 汪文勇. 2400 m埋深地下实验室洞群布置模式优化研究[J]. 岩土工程学报, 2016, 38(z2): 250-254. DOI: 10.11779/CJGE2016S2041
引用本文: 邱治强, 高明忠, 谢晶, 张朝鹏, 汪文勇. 2400 m埋深地下实验室洞群布置模式优化研究[J]. 岩土工程学报, 2016, 38(z2): 250-254. DOI: 10.11779/CJGE2016S2041
QIU Zhi-qiang, GAO Ming-zhong, XIE Jing, ZHANG Zhao-peng, WANG Wen-yong. Optimization of layout pattern of underground laboratory cavern groups with buried depth of 2400 m[J]. Chinese Journal of Geotechnical Engineering, 2016, 38(z2): 250-254. DOI: 10.11779/CJGE2016S2041
Citation: QIU Zhi-qiang, GAO Ming-zhong, XIE Jing, ZHANG Zhao-peng, WANG Wen-yong. Optimization of layout pattern of underground laboratory cavern groups with buried depth of 2400 m[J]. Chinese Journal of Geotechnical Engineering, 2016, 38(z2): 250-254. DOI: 10.11779/CJGE2016S2041

2400 m埋深地下实验室洞群布置模式优化研究  English Version

基金项目: 四川省科技厅应用基础计划项目(2015JY0045); 国家重点
详细信息
    作者简介:

    邱治强(1991- ),男,重庆垫江人,硕士研究生,主要从事岩土工程方面研究。E-mail: 957719062@qq.com。

Optimization of layout pattern of underground laboratory cavern groups with buried depth of 2400 m

  • 摘要: 深部地下试验室是未来人类开采深部资源的基础,中国锦屏地下实验室是全世界埋深最深的地下实验室,锦屏地下试验室二期#8实验洞的建设或许涉及极深岩石力学研究方向,故拟在#8实验洞内设计开挖多个实验洞群以开展原位力学测试及原理探索。然而,实验洞群的布置模式直接影响地下实验室的长期稳定特性。针对高地应力赋存环境地下实验洞室群开挖,建立了FLAC3D三维数值模型,对比研究了同侧相邻洞室不同间距和异侧洞室不同布置工况下,后续洞室开挖对已建洞室围岩稳定性的影响,并用位移变化值作为地下洞室群布置工况评价指标,判识开挖对已建洞室的影响程度。结果表明:同侧相邻洞室间距8 m,异侧洞室对称布置为最优布置工况。研究成果可直接指导锦屏地下实验室二期#8实验洞内实验洞群的布置设计,为其他高地应力环境下洞室群布置提供参考。
    Abstract: Deep underground laboratory is the foundation of deep mining resources in the future. Jinping underground laboratory in China is the deepest underground laboratory in the world. The construction of No. 8 experimental cavern may involve the research of deep rock mechanics, so multiple caverns will be designed and excavated to carry out in-situ mechanics tests and principle exploration. However, the stability of underground laboratory is directly influenced by the layout pattern of cavern groups. Therefore, aiming at the excavation of the underground experimental caverns under high geostress, a 3D numerical model is established by FLAC. The influences of excavation of the subsequent caverns on the stability of surrounding rock of excavated caverns are compared, which include different spacings at the same side and different layouts at opposite sides, then the value of displacement is introduced to identify the influences of excavation on the caverns which are built. The result shows that the layout with the spacing of 8 m at the same side and the symmetry at opposite sides is optimal. They may guide the layout of underground cavern groups in Jinping’s No. 8 laboratory. Moreover, it can offer a reference for the layout of other similar underground projects.
  • [1] 刘世煌, 吴 熹. 拉西瓦水电站高地应力地区大型地下厂房洞群围岩稳定性研究[J]. 水力发电, 1995(3): 17-21. (LIU Shi-huang, WU Xi. Surrounding rock stability study of huge hydropower station under high geostress filed[J]. Journal Hydroelectric Power, 1995(3): 17-21. (in Chinese))
    [2] 谢和平. 深部高应力下的资源开采与地下工程——机遇与挑战[C]// 香山科学会议第175次学术讨论会——深部高应力下的资源开采与地下工程. 北京, 2001: 1-9. (XIE He-ping. Opportunity and Challenge of resource mining and underground engineering under deep high geostress[C]// Xiangshan Academic Conference Discussion No. 175—Basic Crucial Problem in Deep Underground Space Exploitation. Beijing, 2001: 1-9. (in Chinese))
    [3] CHRYSSANTHAKIS P, BARTON N. Dynamic loading of physical and numerical models of very large[C]// Proc of 8 th Conferen-ce on Rock Mech. Tokyo, 1995: 1313-1316.)
    [4] DASGUPTA B, DHAM R, LORIG L J. Three dimensional discontinue analysis of the underground power house for Sardar Sarovar Project, India[C]// Proc. of 8 th Int Conference on Rock Mech. Tokyo, 1995: 551-554.
    [5] DASGUPTA B, SHARMA M K V, VERMAN, et al. Design of underground caverns for Tehri Hydropower Project, India by numerical modeling[C]// Proc of 9 th Int Conference on Rock Mech. Pairs, 1991: 357-358.
    [6] LEE Y N, SUH Y H, KIM D Y, et al. Three-dimensional behavior of large rock caverns[C]// Proc.of 8 th Int. Conference on Rock Mechanics. Tokyo, 1995: 505-508.
    [7] 付 敬, 董志宏, 丁秀丽, 等. 高地应力下深埋隧洞软岩段围岩时效特征研究[J]. 岩土力学, 2011, 32(增刊2): 444-448. (FU Jing, DONG Zhi-hong, DING Xi-uli, et al. Study of aging characteristics of soft surrounding rock in deep tunnel with high ground stress[J]. Rock and Soil Mechanics, 2011, 32(S2): 444-448. (in Chinese))
    [8] 王水林, 李春光, 史贵才, 等. 小湾水电站地下厂房洞室群弹脆塑性分析[J]. 岩石力学与工程学报, 2005, 24(24): 4449-4454. (WANG Shui-lin, LI Chun-guang, SHI Gui-cai, et al. Analysis of underground powerhouses in Xiaowan Hydro-power station by elastic-brittle-plastic constitutive model[J]. Chinese Journal Rock Mechanics and Engineering, 2005, 24(24): 4449-4454. (in Chinese))
    [9] 江 权, 冯夏庭, 陈国庆, 等. 高地应力下拉西瓦水电站地下洞室群稳定性分析[J]. 水利发电学报, 2010, 29(5): 132-140. (JIANG Quan, FENG Xia-ting, CHEN Guo-qing, et al. Stability analysis of large underground caverns in Laxiwa hydropower plant under high crustal stress[J]. Journal of Hydroelectric Engineering, 2010, 29(5): 132-140. (in Chinese))
    [10] 罗 忆, 卢文波, 周创兵, 等. 高地应力条件下地下厂房开挖动态卸荷引起的变形突变机制研究[J]. 岩土力学, 2011, 32(5): 1553-1560. (LUO Yi, LU Wen-bo, ZHOU Chuang-bing, et al. Mechanism study of abrupt deformation of underground powerhouse induced by excavation unloading under high in-situstress[J]. Rock and Soil Mechanic, 2011, 32(5): 1553-1560. (in Chinese))
    [11] 朱维申, 李 勇, 张 磊, 等. 高地应力条件下洞室群稳定性的地质力学模型实验研究[J]. 岩石力学与工程学报, 2008, 27(7): 1308-1314. (ZHU Wei-shen, LI Yong, ZHANG Lei, et al. Geomechanical model test on stability of cavern group under high crustal stress[J]. Chinese Journal of Rock Mechanics and Engineering, 2008, 27(7): 1308-1314. (in Chinese))
    [12] 陈景涛, 朱进明, 苏国韶. 高地应力下地下洞室群开挖过程的数值模拟[J]. 华中科技大学学报, 2009, 26(4): 5-9. (CHEN Jing-tao, ZHU Jing-ming, SU Guo-shao. The numerical simulation of cavern group excavation under high crustal stress[J]. Journal of Huazhong University of Science and Technology, 2009, 26(4): 5-9. (in Chinese))
    [13] 江 权, 冯夏庭, 陈建林. 锦屏二级水电站厂址区域三维地应力非线性反演[J]. 岩土力学, 2008, 29(11): 3003-3010. (JIANG Quan, FENG Xia-ting, CHEN Jian-lin. Nonlinear inversion of 3D initial geostress field in Jinping Ⅱ Hydropower Station region[J]. Rock and Soil Mechanics, 2008, 29(11): 3003-3010. (in Chinese))
  • 期刊类型引用(2)

    1. 占鑫杰,吕冲,桂书润,李振亚. 化学调质及固结作用下市政污泥水分转化规律. 科学技术与工程. 2025(05): 2057-2065 . 百度学术
    2. 张玉伟,宋战平,谢永利. 孔隙变化条件下黄土土水特征曲线预测模型. 岩土工程学报. 2022(11): 2017-2025 . 本站查看

    其他类型引用(4)

计量
  • 文章访问数: 
  • HTML全文浏览量:  0
  • PDF下载量: 
  • 被引次数: 6
出版历程
  • 收稿日期:  2016-05-18
  • 发布日期:  2016-10-19

目录

    /

    返回文章
    返回