基于北斗的机场高填方施工质量监控技术研发

姚仰平, 阮杨志, 刘冰阳, 陈军, 姜宏旭

姚仰平, 阮杨志, 刘冰阳, 陈军, 姜宏旭. 基于北斗的机场高填方施工质量监控技术研发[J]. 岩土工程学报, 2015, 37(zk2): 6-10. DOI: 10.11779/CJGE2015S2002
引用本文: 姚仰平, 阮杨志, 刘冰阳, 陈军, 姜宏旭. 基于北斗的机场高填方施工质量监控技术研发[J]. 岩土工程学报, 2015, 37(zk2): 6-10. DOI: 10.11779/CJGE2015S2002
YAO Yang-ping, RUAN Yang-zhi, LIU Bing-yang, CHEN Jun, JIANG Hong-xu. Control technology of construction quality for high filled airport based on Beidou satellite navigation system[J]. Chinese Journal of Geotechnical Engineering, 2015, 37(zk2): 6-10. DOI: 10.11779/CJGE2015S2002
Citation: YAO Yang-ping, RUAN Yang-zhi, LIU Bing-yang, CHEN Jun, JIANG Hong-xu. Control technology of construction quality for high filled airport based on Beidou satellite navigation system[J]. Chinese Journal of Geotechnical Engineering, 2015, 37(zk2): 6-10. DOI: 10.11779/CJGE2015S2002

基于北斗的机场高填方施工质量监控技术研发  English Version

基金项目: 国家重点基础研究发展计划(“973”计划)(2014CB047006)
详细信息
    作者简介:

    姚仰平(1960- ),男,陕西西安人,博士,教授,博士生导师,主要从事土的基本特性和本构模型研究。

Control technology of construction quality for high filled airport based on Beidou satellite navigation system

  • 摘要: 山区机场高填方质量监控主要针对干密度进行监控,传统的监控手段均属事后检测、操作上以点代面,需要加强施工质量过程监控并对其进行快速监测。针对山区机场高填方质量监控的要求,在建立冲击碾压质量实时监测指标和要求的基础上,采用北斗卫星导航定位和3G无线传输技术,提出了机场高填方冲击碾压质量实时监控方法,以及冲击碾压过程的信息实时采集传输技术和GIS平台的冲击碾压过程可视化等主要技术,实现了冲击碾压轨迹、速度和遍数等施工信息的全过程实时监测。施工现场的初步试验表明,该技术能有效应用于山区机场,对提高机场高填方施工质量具有重要意义。
    Abstract: The quality control for the embankment of airport in mountain areas at present is mainly based on the control of dry density of soils. The traditional control methods estimate the construction quality of the entire area by monitoring a limited number of representative points, which is difficult to ensure the rolling quality effectively or to monitor the real-time compaction quality. According to the characteristics of high embankment quality control for mountainous airports, real-time monitoring indices and criteria are established. Using the Beidou satellite navigation system and 3G wireless transmission technology, the real-time monitoring method of impact rolling for high embankment of airport is proposed. Combining the real-time collecting technology and visualization technology, the real-time monitoring of the whole process about track, speed and number of compaction is realized. The tests at the construction site show that this technology can be effectively applied for mountainous airports in cost control, project management and quality monitoring, which is significant for improving the construction quality of high embankment of airport.
  • [1] 曹光栩, 宋二祥, 徐 明. 山区机场高填方地基工后沉降变形简化算法[J]. 岩土力学, 2011, 32(1): 1-5. (CAO Guang-xu, SONG Er-xiang, XU Ming. Simplified calculation methods of post-construction settlement of high-fill foundation in mountain airport[J]. Rock and Soil Mechanics, 2011, 32(1): 1-5. (in Chinese))
    [2] MARK J T, DAVID J W. Estimating compaction of cohesive soils from machine drive power[J]. Journal of Geotechinical and Geoenvironmental Engineering, 2008, 134(12): 1771-1777.
    [3] DAVID J W, MARK J T. Relationships between in situ and roller-integrated compaction measurements for granular soils[J]. Journal of Geotechinical and Geoenvironmental Engineering, 2008, 134(12): 1763-1770.
    [4] MICHAEL A M, ROBERT V R. Field monitoring of roller vibration during compaction of subgrade soil[J]. Journal of Geotechinical and Geoenvironmental Engineering, 2007, 133(3): 257-265.
    [5] PETERSEN D, SIEEKMEIER J, NELSON C, et al. Intelligent soil compaction-technology, results and a roadmap toward widespread use[J]. Journal of Transport Research Board, 2006, 1975(1): 81-88.
    [6] 黄声享, 刘经南. GPS 实时监控系统及其在堆石坝施工中的初步应用[J]. 武汉大学学报, 2005, 30(9): 813-816. (HUANG Sheng-xiang, LIU Jing-nan. GPS real-time supervisory system and its preliminary applicationin the construction of face rockfill dam[J]. Geomatics and Information Science of Wuhan University, 2005, 30(9): 813-816. (in Chinese))
    [7] 吴晓铭, 黄声享. 水布垭水电站大坝填筑碾压施工质量监控系统[J]. 水力发电, 2008, 34(3): 47-50. (WU Xiao-ming, HUANG Sheng-xiang. Quality supervisory system of filling and rolling construction in the dam of Shuibuya hydropower station[J]. Water Power, 2008, 34(3): 47-50. (in Chinese))
    [8] ZHONG Deng-hua, CUI Bo,LIU Dong-hai. Theoretical research on construction quality real-time monitoring and system integration of core rockfill dam[J]. Science in China Series E-Technological Sciences, 2009, 52(11): 3406-3412.
    [9] 田 昊, 张东宁. 九寨黄龙机场高填方施工技术[J]. 山西建筑, 2010, 36(7): 63-64. (TIAN Hao, ZHANG Dong-ning. The high fill construction technology of Jiuzhai Huanglong airport[J]. Shanxi Architecture, 2010, 36(7): 63-64. (in Chinese))
    [10] 谭述森, 周 兵, 郭盛桃, 等. 我国全球卫星导航信号设计研究[J]. 中国科学: 物理学 力学 天文学, 2010, 40(5): 514-519. (TAN Shu-sen, ZHOU Bing, GUO Sheng-tao, et al. Studies of compass navigation signals design[J]. Science China, 2010, 40(5): 514-519. (in Chinese))
    [11] YANG Yuan-xi, LI Jin-long, WANG Ai-bing, et al. Preliminary assessment of the navigation and positioning performance of Beidou regional navigation satellite system[J]. Science China: Earth Sciences, 2014, 57: 144-152.
    [12] SHI Chuang, ZHAO Qi-le, LI Min, et al. Precise orbit determination of Beidou satellites with precise positioning. Science China: Earth Science, 2012, 55: 1079-1086.
    [13] 姚作新. 基于北斗卫星短信通信方式的无人值守自动气象站网[J]. 气象科技, 2012, 40(3): 340-344. (YAO Zuo-xin. Unmanned automatic weather station network based on Beidou satellite SMS[J]. Meteorological Science and Technology, 2012, 40(3): 340-344. (in Chinese))
    [14] 王文松, 蓝常源, 陈 涛. 基于北斗系统驾校考试终端设计研究[J]. 卫星与网络, 2013 (5): 68-71. (WANG Wen-song, LAN Chang-yuan, CHEN Tao. Driving test terminal based on Beidou satellite[J]. Satellite and Network, 2013(5): 68-71. (in Chinese))
    [15] 徐 坤, 周正飞. 承德民用机场高填方边坡稳定性分[J]. 公路工程, 2014, 39(2): 251-257. (XU Kun, ZHOU Zheng-fei. Stability analysis of high fill slope of Chengde civil airport[J]. Highway Engineering, 2014, 39(2): 251-257. (in Chinese))
计量
  • 文章访问数:  312
  • HTML全文浏览量:  3
  • PDF下载量:  409
  • 被引次数: 0
出版历程
  • 收稿日期:  2015-03-25
  • 发布日期:  2015-07-24

目录

    /

    返回文章
    返回