逆作法中立柱调垂方法探讨

盛春陵, 李仁民, 王守超, 陈波

盛春陵, 李仁民, 王守超, 陈波. 逆作法中立柱调垂方法探讨[J]. 岩土工程学报, 2012, 34(suppl): 595-597.
引用本文: 盛春陵, 李仁民, 王守超, 陈波. 逆作法中立柱调垂方法探讨[J]. 岩土工程学报, 2012, 34(suppl): 595-597.
SHENG Chun-ling, LI Ren-min, WANG Shou-chao, CHEN Bo. Vertical adjustment method for soldier piles in top-down projects[J]. Chinese Journal of Geotechnical Engineering, 2012, 34(suppl): 595-597.
Citation: SHENG Chun-ling, LI Ren-min, WANG Shou-chao, CHEN Bo. Vertical adjustment method for soldier piles in top-down projects[J]. Chinese Journal of Geotechnical Engineering, 2012, 34(suppl): 595-597.

逆作法中立柱调垂方法探讨  English Version

详细信息
    作者简介:

    盛春陵(1963– ),上海市人,一级注册结构工程师,主要从事结构设计工作。

  • 中图分类号: TU75

Vertical adjustment method for soldier piles in top-down projects

  • 摘要: 逆作法施工中,立柱由于需承受较大的竖向荷载,设计施工中需严格控制立柱的垂直度。本文总结了目前常用的立柱垂直度控制方法,并对各方法的适用性及优缺点进行了分析。同时,结合南京某逆作法工程,提出了一套钢管立柱垂直度质量控制体系,对今后逆作法的施工,有一定的指导意义。
    Abstract: In top-down projects, due to the need to bear large vertical loads, the design and construction of soldier piles should strictly control their vertical degrees. The most commonly used column verticality control methods are reviewed, and their applicabilities, advantages and disadvantages are analyzed. At the same time, combined with a top-down project in Nanjing, the quality control system of steel pipe soldier piles is proposed. It will have guiding significance for the future construction of top-down projects.
  • [1] 吴 献, 唐 彪. 逆作法中几种立柱的调垂方法[J]. 建筑技术, 2004, 35(2): 137–138. (WU Xian, TANG Biao. Inverse practices of several tune vertical column construction technology[J]. Construction Technology, 2004, 35(2): 137–138. (in Chinese))
    [2] DG/TJ08—61—2010 基坑工程技术规范[S]. (DG/TJ08—61—2010 Technical code for excavation engineering[S]. (in Chinese))
    [3] 康 忠. 逆作法施工中一柱一桩的施工方法与技术保证措施[J]. 建筑施工, 1999, 21(3): 38–40. (KANG Zhong. Reverse construction of a column of a construction method and technology to ensure measures[J]. Building Construction, 1999, 21(3): 38–40. (in Chinese))
    [4] 卢永存. 建筑结构逆作区一柱一桩工程施工技术[J]. 建筑施工, 2005, 27(10): 35–42. (LU Yong-cun. Engineering technology of one column one pile for area of architectural structure with top-down construction method[J]. Building Construction,2005, 27(10): 35–42. (in Chinese))
    [5] 顾国明. 超长钢格构柱垂直度实时监控系统[J]. 施工技术, 2009, 8: 53–56. (GU Guo-ming. Real-time monitoring system of super-long steel lattice column verticality[J]. Construction Mechanization, 2009, 8: 53–56. (in Chinese))
    [6] 廖秋林. 南京德基广场逆作法超深支撑桩柱施工技术[J]. 建筑技术, 2009, 38(9): 60–63. (LIAO Qiu-lin. Reverse construction technology of super-deep support piles and columns in Nanjing Deji Plaza[J]. Construction Technology, 2009, 38(9): 60–63. (in Chinese))
    [7] 吴 献, 李定江, 张为江. 逆作法施工中支承格构柱采用气囊法智能调垂施工技术[J]. 建筑施工, 2003, 25(1): 12–14. (WU Xian, LI Ding-jiang, ZHANG Wei-jiang. Intellectualized technique for making supporting lattice column perpendicular by air cell in top-down construction method[J]. Building Construction, 2003, 25(1): 12–14. (in Chinese))
    [8] 杨学林, 周平槐. 逆作地下室设计中的若干关键问题[J]. 岩土工程学报, 2010, 32(增刊1): 238–244. (YANG Xue-lin, ZHOU Ping-huai. Some key problems in design of basements using top-down method[J]. Chinese Journal of Geotechnical Engineering, 2010, 32(S1): 238–244. (in Chinese))
计量
  • 文章访问数:  855
  • HTML全文浏览量:  0
  • PDF下载量:  660
  • 被引次数: 0
出版历程
  • 收稿日期:  2012-11-12
  • 发布日期:  2012-11-12